New Project

50 Crossroads, YMCA Cross Road, Calicut

PILING WORK PROGRESS 31.10.2016
PILING WORK 30.11.2016
PILING WORK COMPLETED ON 16.01.2017
PILE LOAD TEST AS ON 28.02.2017
WORK STATUS AS ON 31.03.2017
RCC FOR GF SLAB
PILING OF RET WALL